CAPM · Question #356
Which Subsidiary management plan would a project manager create to manage information dissemination during the project life cycle?
The correct answer is A. Stakeholder Engagement Plan. NOTE: The marked answer appears to be incorrect. The Communications Management Plan (C) is the subsidiary plan specifically designed to manage information dissemination throughout the project life cycle. It defines how project information is created, distributed, stored, retrieve
Question
Options
- AStakeholder Engagement Plan
- BQuality Management Plan
- CCommunications Management Plan
- DScope Management Plan
How the community answered
(30 responses)- A90% (27)
- C3% (1)
- D7% (2)
Explanation
NOTE: The marked answer appears to be incorrect. The Communications Management Plan (C) is the subsidiary plan specifically designed to manage information dissemination throughout the project life cycle. It defines how project information is created, distributed, stored, retrieved, and disposed of. The Stakeholder Engagement Plan (A) addresses strategies and actions needed to promote stakeholder involvement and manage expectations - it is not primarily about information dissemination. For exam purposes, if the question specifically references 'information dissemination,' the Communications Management Plan is the correct answer per PMBOK.