CAPM · Question #287
Which three of the following interpersonal skills does a project manager rely on when developing the project management plan? (Choose three.)
The correct answer is A. Conflict management B. Facilitation D. Meeting management. Developing the project management plan requires interpersonal skills that help the PM work collaboratively with the team and stakeholders. Conflict management, facilitation, and meeting management are interpersonal skills, while interviews and focus groups are elicitation…
Question
Options
- AConflict management
- BFacilitation
- CInterviews
- DMeeting management
- EFocus groups
How the community answered
(25 responses)- A96% (24)
- E4% (1)
Why each option
Developing the project management plan requires interpersonal skills that help the PM work collaboratively with the team and stakeholders. Conflict management, facilitation, and meeting management are interpersonal skills, while interviews and focus groups are elicitation techniques.
Interviews are an elicitation and information-gathering technique, not an interpersonal skill used in the context of plan development.
Focus groups are a requirements-gathering and elicitation technique, not an interpersonal skill applied during planning.
Concept tested: Interpersonal skills in project management plan development
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok