nerdexam
PMI

CAPM · Question #374

Which statement describes the various purposes of project scheduling?

The correct answer is D. Define activities, sequences, duration, and dependencies; serve as a reference for resource allocation, serve as a base for earned value analysis. Option D correctly captures the multi-dimensional purpose of project scheduling: it defines the project's activities, their sequences, durations, and dependencies (the structural purpose), serves as a reference for allocating resources to activities (the planning purpose), and…

Predictive Plan-Based Methodologies

Question

Which statement describes the various purposes of project scheduling?

Options

  • ADefine the policies, rules, and techniques to run a schedule; serve as a tool to manage stakeholder expectations, and serve as a base for backlog management
  • BDefine how and when deliverables will be completed, serve as communication tool, and serve as a base for performance reporting
  • CDefine the life cycle, traditional or agile approach, and tools to control schedule; serve as a reference for scope management, and serve as a base for risk management
  • DDefine activities, sequences, duration, and dependencies; serve as a reference for resource allocation, serve as a base for earned value analysis.

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    3% (1)
  • D
    94% (30)

Explanation

Option D correctly captures the multi-dimensional purpose of project scheduling: it defines the project's activities, their sequences, durations, and dependencies (the structural purpose), serves as a reference for allocating resources to activities (the planning purpose), and forms the basis for earned value analysis - allowing actual performance to be measured against planned values (the control purpose). Option A incorrectly describes characteristics of the schedule management plan and mixes in backlog management (agile-specific). Option B is partially correct but incomplete. Option C conflates scheduling with lifecycle decisions, scope management, and risk management - which are separate processes.

Topics

#Project Scheduling#Schedule Management#Resource Management#Earned Value Analysis

Community Discussion

No community discussion yet for this question.

Full CAPM Practice