CAPM · Question #206

CAPM Question #206: Real Exam Question with Answer & Explanation

The correct answer is C: Project charter, project management plan, and project documents. See the full explanation below for the reasoning.

Predictive Plan-Based Methodologies

Question

The project manager is creating the communications management plan. Which group of inputs is required to begin?

Options

  • AWork performance reports, change requests, and risk register
  • BWork performance data, project documents, and stakeholder engagement plan
  • CProject charter, project management plan, and project documents
  • DWork performance data, stakeholder register, and team management plan

Topics

#Communications Management#Planning Process Group#Inputs#PMBOK ITTOs