CAPM · Question #206
The project manager is creating the communications management plan. Which group of inputs is required to begin?
The correct answer is C. Project charter, project management plan, and project documents. Per the PMBOK Guide, the inputs to the Plan Communications Management process are: Project charter, Project management plan (which includes subsidiary plans), Project documents (such as the stakeholder register and requirements documentation), Enterprise environmental factors…
Question
Options
- AWork performance reports, change requests, and risk register
- BWork performance data, project documents, and stakeholder engagement plan
- CProject charter, project management plan, and project documents
- DWork performance data, stakeholder register, and team management plan
How the community answered
(63 responses)- A5% (3)
- B2% (1)
- C92% (58)
- D2% (1)
Explanation
Per the PMBOK Guide, the inputs to the Plan Communications Management process are: Project charter, Project management plan (which includes subsidiary plans), Project documents (such as the stakeholder register and requirements documentation), Enterprise environmental factors, and Organizational process assets. Answer C correctly identifies the three primary project-based inputs. Work performance data and work performance reports (A, B, D) are inputs to monitoring and controlling processes, not planning processes. The stakeholder engagement plan is an output of planning, not an input to communications planning.