PMIPMI
CAPM · Question #206
CAPM Question #206: Real Exam Question with Answer & Explanation
The correct answer is C: Project charter, project management plan, and project documents. See the full explanation below for the reasoning.
Predictive Plan-Based Methodologies
Question
The project manager is creating the communications management plan. Which group of inputs is required to begin?
Options
- AWork performance reports, change requests, and risk register
- BWork performance data, project documents, and stakeholder engagement plan
- CProject charter, project management plan, and project documents
- DWork performance data, stakeholder register, and team management plan
Topics
#Communications Management#Planning Process Group#Inputs#PMBOK ITTOs
Community Discussion
No community discussion yet for this question.