A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

The correct answer is C. review and update stakeholder engagement. Phase transitions are natural checkpoints - sometimes called phase gates or stage gates - where the project manager should review and update stakeholder engagement. As the project moves into a new phase, stakeholder priorities, influence, and expectations may shift, making it…

Predictive, Plan-Based Methodologies

Question

A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

Options

  • Acreate the project management plan.
  • Bidentify the project objectives.
  • Creview and update stakeholder engagement.
  • Dcreate the schedule baseline.

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    19% (4)
  • C
    71% (15)
  • D
    5% (1)

Explanation

Phase transitions are natural checkpoints - sometimes called phase gates or stage gates - where the project manager should review and update stakeholder engagement. As the project moves into a new phase, stakeholder priorities, influence, and expectations may shift, making it critical to reassess engagement strategies. The project management plan (A) and project charter (B) are created at project initiation, not at phase transitions. The schedule baseline (D) is established during planning and is not re-created at phase transitions under normal circumstances.

Topics

#Project phases#Stakeholder engagement#Phase gate#Ongoing processes