CAPM · Question #208

CAPM Question #208: Real Exam Question with Answer & Explanation

The correct answer is C: 36. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

Options

  • A8
  • B18
  • C36
  • D40

Topics

#Communication channels#Communication management#Stakeholder management