CAPM · Question #209
A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to capture stakeholder interest?
The correct answer is D. Communication skills and cultural awareness. When meeting directly with crucial stakeholders to capture their interests, the project manager relies on interpersonal and team skills - specifically communication skills (active listening, open-ended questioning, facilitation) and cultural awareness (understanding…
Question
Options
- AReview stakeholder register and meeting
- BData analysis and communication skills
- CData gathering and data analysis
- DCommunication skills and cultural awareness
How the community answered
(37 responses)- A3% (1)
- B5% (2)
- C14% (5)
- D78% (29)
Explanation
When meeting directly with crucial stakeholders to capture their interests, the project manager relies on interpersonal and team skills - specifically communication skills (active listening, open-ended questioning, facilitation) and cultural awareness (understanding stakeholders' backgrounds, values, and perspectives to engage them effectively). A stakeholder register (A) is an artifact, not a technique for capturing interest. Data analysis (B, C) is used after information is gathered. Cultural awareness is particularly important at project initiation when the project manager may not yet know the stakeholders well.