nerdexam
PMI

CAPM · Question #210

Select three processes that are associated with Project Schedule Management? (Choose three.)

The correct answer is A. Define Activities C. Estimate Activity Durations D. Develop Schedule. Project Schedule Management includes six processes: Plan Schedule Management, Define Activities (A), Sequence Activities, Estimate Activity Durations (C), Develop Schedule (D), and Control Schedule. Plan Resource Management (B) and Acquire Resources (E) both belong to Project…

Predictive Plan-Based Methodologies

Question

Select three processes that are associated with Project Schedule Management? (Choose three.)

Options

  • ADefine Activities
  • BPlan Resource Management
  • CEstimate Activity Durations
  • DDevelop Schedule
  • EAcquire Resources

How the community answered

(61 responses)
  • A
    89% (54)
  • B
    5% (3)
  • E
    7% (4)

Explanation

Project Schedule Management includes six processes: Plan Schedule Management, Define Activities (A), Sequence Activities, Estimate Activity Durations (C), Develop Schedule (D), and Control Schedule. Plan Resource Management (B) and Acquire Resources (E) both belong to Project Resource Management, not Schedule Management. The key distinction is that scheduling focuses on timing and sequencing of work, while resource management focuses on identifying, obtaining, and managing the people and materials needed.

Topics

#Project Schedule Management#PMBOK Processes#Planning Process Group

Community Discussion

No community discussion yet for this question.

Full CAPM Practice