CAPM · Question #210
Select three processes that are associated with Project Schedule Management? (Choose three.)
The correct answer is A. Define Activities C. Estimate Activity Durations D. Develop Schedule. Project Schedule Management includes six processes: Plan Schedule Management, Define Activities (A), Sequence Activities, Estimate Activity Durations (C), Develop Schedule (D), and Control Schedule. Plan Resource Management (B) and Acquire Resources (E) both belong to Project…
Question
Options
- ADefine Activities
- BPlan Resource Management
- CEstimate Activity Durations
- DDevelop Schedule
- EAcquire Resources
How the community answered
(61 responses)- A89% (54)
- B5% (3)
- E7% (4)
Explanation
Project Schedule Management includes six processes: Plan Schedule Management, Define Activities (A), Sequence Activities, Estimate Activity Durations (C), Develop Schedule (D), and Control Schedule. Plan Resource Management (B) and Acquire Resources (E) both belong to Project Resource Management, not Schedule Management. The key distinction is that scheduling focuses on timing and sequencing of work, while resource management focuses on identifying, obtaining, and managing the people and materials needed.
Topics
Community Discussion
No community discussion yet for this question.