The correct answer is A: Plan Quality Management, Manage Quality, and Control Quality. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What are the project management processes associated with project quality management?
Options
- APlan Quality Management, Manage Quality, and Control Quality
- BPlan Quality Management, Manage Quality, and Cost of Quality
- CManage Quality, Customer Satisfaction, and Control Quality
- DCustomer Satisfaction, Control Quality, and Continuous Improvement
Topics
#Project Quality Management#PMBOK Processes#Process Groups#Quality Planning and Control