CAPM · Question #212
CAPM Question #212: Real Exam Question with Answer & Explanation
The correct answer is B: Giving access to information to the team and frequent team checkpoints. See the full explanation below for the reasoning.
Adaptive Frameworks/Methodologies
Question
In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with charges?
Options
- AHaving control over the planning and delivery of the products without delegating decisions
- BGiving access to information to the team and frequent team checkpoints
- CSelecting different team members to take the project manager role during reviews with Stakeholders
- DAsking the control change board to approve changes before notifying the team
Topics
#Adaptive project management#Change management#Team communication#Transparency