The activity of tailoring is necessary because:
Options
- Athe members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide; this is required for all projects.
- Beach project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide.
- Cthe members of the project team need to understand the PMBOK Guide processes, which are applied to all projects.
- Deach project is unique, and the project team must plan how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide.