CAPM · Question #96

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement management does this project require?

The correct answer is C. Engaging regularly with stakeholders. Projects with a high degree of change require frequent and proactive stakeholder engagement to manage evolving expectations and maintain alignment.

Adaptive Frameworks/Methodologies

Question

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement management does this project require?

Options

  • ADiscussing with management
  • BEscalating to the sponsors
  • CEngaging regularly with stakeholders
  • DEngaging only with decision makers

How the community answered

(41 responses)
  • A
    5% (2)
  • C
    93% (38)
  • D
    2% (1)

Why each option

Projects with a high degree of change require frequent and proactive stakeholder engagement to manage evolving expectations and maintain alignment.

ADiscussing with management

Discussing only with management limits engagement to a single tier and does not address the broader stakeholder base affected by frequent changes.

BEscalating to the sponsors

Escalating to sponsors is a reactive action taken when issues cannot be resolved at the project level, not a proactive engagement strategy for high-change projects.

CEngaging regularly with stakeholdersCorrect

In high-change environments, the PMBOK Manage Stakeholder Engagement process and agile principles both emphasize continuous, regular interaction with stakeholders to surface issues early, adjust expectations, and maintain trust. Ongoing engagement ensures stakeholders remain informed and supportive as the project adapts to change.

DEngaging only with decision makers

Engaging only with decision makers excludes other stakeholders whose support, input, or concerns are critical to successfully navigating a high-change environment.

Concept tested: Stakeholder engagement strategy in high-change environments

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Stakeholder Engagement#Project Change#Adaptive Principles#Communication Management