PMIPMI
CAPM · Question #461
CAPM Question #461: Real Exam Question with Answer & Explanation
The correct answer is D: Project management plan. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project team member is reviewing the scope of a task with an end user and realizes that requirements have changed. Which project artifact should be used in this situation?
Options
- AScope management plan
- BRisk management plan
- CConfiguration management plan
- DProject management plan
Topics
#Change Management#Project Management Plan#Scope Management#Requirements Management
Community Discussion
No community discussion yet for this question.