nerdexam
PMIPMI

CAPM · Question #461

CAPM Question #461: Real Exam Question with Answer & Explanation

The correct answer is D: Project management plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project team member is reviewing the scope of a task with an end user and realizes that requirements have changed. Which project artifact should be used in this situation?

Options

  • AScope management plan
  • BRisk management plan
  • CConfiguration management plan
  • DProject management plan

Topics

#Change Management#Project Management Plan#Scope Management#Requirements Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions