CAPM Question #462: Real Exam Question with Answer & Explanation
The correct answer is A: Tasks that create business value should be done first.. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
How should the product owner prioritize a list of tasks to be accomplished?
Options
- ATasks that create business value should be done first.
- BTasks that can be completed quickly should be done first.
- CTasks that reduce the product backlog should be done first.
- DTasks that enhance the functionality of a product should be done first.
Topics
#Product Owner#Prioritization#Business Value#Agile Principles