nerdexam
PMIPMI

CAPM · Question #205

CAPM Question #205: Real Exam Question with Answer & Explanation

The correct answer is C: Earned value analysis (EVA). See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What should a project manager use to determine how much money is needed to complete a project?

Options

  • AEarned value management (EVM)
  • BEstimate at completion (EAC)
  • CEarned value analysis (EVA)
  • DBudget at completion (BAC)

Topics

#Earned Value Analysis (EVA)#Cost Management#Project Performance Measurement#Forecasting

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions