CAPM · Question #373

During project execution, a team member has identified and then analyzed an opportunity that will yield a net savings of 10% and reduce time in the schedule by 20% Which strategy should the project…

The correct answer is B. Exploit the opportunity immediately, since the cost saving makes it worthwhile. In PMBOK risk management, 'Exploit' is the strategy used when a project team wants to ensure that an identified opportunity is realized. Since the opportunity has already been identified AND analyzed - showing a confirmed 10% cost reduction and 20% schedule improvement…

Predictive, Plan-Based Methodologies

Question

During project execution, a team member has identified and then analyzed an opportunity that will yield a net savings of 10% and reduce time in the schedule by 20% Which strategy should the project manager adopt to accommodate this opportunity?

Options

  • AEscalate to upper management to build awareness of the opportunity
  • BExploit the opportunity immediately, since the cost saving makes it worthwhile.
  • CTransfer the opportunity to a partner and start a partner contract.
  • DCreate a trail of the opportunity before full adoption, because of the risk associated.

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    74% (17)
  • C
    9% (2)
  • D
    13% (3)

Explanation

In PMBOK risk management, 'Exploit' is the strategy used when a project team wants to ensure that an identified opportunity is realized. Since the opportunity has already been identified AND analyzed - showing a confirmed 10% cost reduction and 20% schedule improvement - exploiting it immediately is the appropriate and logical response. The analysis provides sufficient justification to act. Option A (escalate) is reserved for opportunities outside the PM's authority to act upon. Option C (transfer) is typically a threat response strategy, not an opportunity strategy. Option D (creating a trial) implies uncertainty about the outcome, but the question states the analysis already confirms the savings - so a cautious pilot is unnecessary.

Topics

#Risk Management#Opportunity Response#Exploit Strategy#Project Execution

Community Discussion

No community discussion yet for this question.