During project execution, a team member has identified and then analyzed an opportunity that will yield a net savings of 10% and reduce time in the schedule by 20% Which strategy should the project manager adopt to accommodate this opportunity?

Options

  • AEscalate to upper management to build awareness of the opportunity
  • BExploit the opportunity immediately, since the cost saving makes it worthwhile.
  • CTransfer the opportunity to a partner and start a partner contract.
  • DCreate a trail of the opportunity before full adoption, because of the risk associated.