nerdexam
PMIPMI

CAPM · Question #372

CAPM Question #372: Real Exam Question with Answer & Explanation

The correct answer is C: Analogous estimating. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

Options

  • ABottom-up estimating
  • BThree-point estimating
  • CAnalogous estimating
  • DParametric estimating

Topics

#Cost Estimation#Analogous Estimating#Estimation Techniques#Project Cost Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions