CAPM · Question #372
A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?
The correct answer is C. Analogous estimating. Analogous estimating uses historical data from previous similar projects as the basis for estimating current project costs, durations, or other parameters. The defining characteristic - referencing past similar project documentation - is the hallmark of this technique. It is gene
Question
Options
- ABottom-up estimating
- BThree-point estimating
- CAnalogous estimating
- DParametric estimating
How the community answered
(29 responses)- B3% (1)
- C93% (27)
- D3% (1)
Explanation
Analogous estimating uses historical data from previous similar projects as the basis for estimating current project costs, durations, or other parameters. The defining characteristic - referencing past similar project documentation - is the hallmark of this technique. It is generally less costly and time-consuming than other methods but also less accurate. Bottom-up estimating (A) involves estimating individual work packages and rolling them up. Three-point estimating (B) uses optimistic, pessimistic, and most likely values. Parametric estimating (D) uses statistical relationships between historical data and project variables (e.g., cost per unit) rather than reviewing documentation from a specific past project.
Topics
Community Discussion
No community discussion yet for this question.