CAPM · Question #371
Which process uses expert judgment to manage project resources?
The correct answer is D. Both A and B. Both Plan Resource Management and Estimate Activity Resources explicitly list expert judgment as a tool and technique in the PMBOK. Plan Resource Management uses expert judgment to determine how resources should be defined, staffed, managed, and released. Estimate Activity…
Question
Options
- APlan Resource Management
- BEstimate Activity Resources
- CManage Team
- DBoth A and B
How the community answered
(52 responses)- A2% (1)
- C4% (2)
- D94% (49)
Explanation
Both Plan Resource Management and Estimate Activity Resources explicitly list expert judgment as a tool and technique in the PMBOK. Plan Resource Management uses expert judgment to determine how resources should be defined, staffed, managed, and released. Estimate Activity Resources uses expert judgment to assess the types and quantities of resources needed for each activity. Therefore, D (Both A and B) is correct. Option C (Manage Team) relies more on interpersonal and team skills, conflict management, and emotional intelligence - while expert judgment may be applied implicitly, it is not a formally listed primary tool/technique for that specific process.
Topics
Community Discussion
No community discussion yet for this question.