PMIPMI
CAPM · Question #288
CAPM Question #288: Real Exam Question with Answer & Explanation
The correct answer is D: Plan the backlog by estimating and reprioritizing the user stories as new information becomes available.. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?
Options
- ADevelop a user story analysis based on the work done, depicting the current status, S-curve, schedule variance (SV), and planned value (PV).
- BRun a spike to ensure all information available is correct and then decide which stories to implement.
- CBring up all risks for implementing the user stories and discuss possible solutions.
- DPlan the backlog by estimating and reprioritizing the user stories as new information becomes available.
Topics
#Agile planning#Backlog refinement#Iteration planning#User story estimation
Community Discussion
No community discussion yet for this question.