PMIPMI
CAPM · Question #316
CAPM Question #316: Real Exam Question with Answer & Explanation
The correct answer is C: Adaptive. See the full explanation below for the reasoning.
Adaptive Frameworks/Methodologies
Question
An organization is faced with increasing demand from the board of directors. They say budgets are flexible as long as the work gets completed. Which project management approach should the organization use?
Options
- APredictive
- BIterative
- CAdaptive
- DHybrid
Topics
#Adaptive approaches#Project methodologies#Evolving requirements#Project flexibility
Community Discussion
No community discussion yet for this question.