What is the next step for a business analyst after the stakeholders have validated the requirements?

Options

  • AUpdate the project management plan.
  • BUpdate the requirements traceability matrix.
  • CUpdate the requirements.
  • DUpdate the work breakdown structure (WBS).

Topics

#Requirements Management#Requirements Traceability Matrix#Business Analyst Role#Validation