PMIPMI
CAPM · Question #474
CAPM Question #474: Real Exam Question with Answer & Explanation
The correct answer is C: Discuss feasible alternatives with functional managers in order to not affect project progress.. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
After a project meeting, Joe (project manager) finds out that some of the resources are not 100% committed to his project and this is causing delays in some project activities. What Joe should do next to resolve this issue?
Options
- ASend a memo to the project team that recalls their commitment to the project.
- BReplace team members that are not 100% committed to the project.
- CDiscuss feasible alternatives with functional managers in order to not affect project progress.
- DAsk upper management to reinforce the project manager's authority over team members.
Topics
#Resource Management#Stakeholder Management#Conflict Resolution#Problem Solving
Community Discussion
No community discussion yet for this question.