nerdexam
PMIPMI

CAPM · Question #474

CAPM Question #474: Real Exam Question with Answer & Explanation

The correct answer is C: Discuss feasible alternatives with functional managers in order to not affect project progress.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

After a project meeting, Joe (project manager) finds out that some of the resources are not 100% committed to his project and this is causing delays in some project activities. What Joe should do next to resolve this issue?

Options

  • ASend a memo to the project team that recalls their commitment to the project.
  • BReplace team members that are not 100% committed to the project.
  • CDiscuss feasible alternatives with functional managers in order to not affect project progress.
  • DAsk upper management to reinforce the project manager's authority over team members.

Topics

#Resource Management#Stakeholder Management#Conflict Resolution#Problem Solving

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions