An organization uses a just-in-time (JIT) measurement system. What units should they use to estimate future work?

The correct answer is C. Cards. In a just-in-time (JIT) measurement system, work is estimated using cards, consistent with Kanban-style flow management where each card represents a unit of work pulled on demand.

Agile Frameworks/Methodologies

Question

An organization uses a just-in-time (JIT) measurement system. What units should they use to estimate future work?

Options

  • AHours
  • BPoints
  • CCards
  • DPackages

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    88% (30)
  • D
    6% (2)

Why each option

In a just-in-time (JIT) measurement system, work is estimated using cards, consistent with Kanban-style flow management where each card represents a unit of work pulled on demand.

AHours

Hours represent time-based estimation, which is more aligned with predictive planning and does not reflect the flow-based, pull-oriented nature of JIT systems.

BPoints

Story points measure relative complexity and are used in sprint-based agile estimation, not specifically tied to JIT or Kanban flow measurement.

CCardsCorrect

JIT systems focus on pulling work only when capacity is available, and in agile/Kanban contexts this is represented by cards - each card is a discrete work item that flows through the system one at a time. Cards as a unit of measurement align with JIT principles by limiting work-in-progress and making throughput visible rather than estimating effort in hours or abstract points.

DPackages

Packages are not a standard unit of measurement in JIT or agile project management frameworks.

Concept tested: JIT measurement using cards in Kanban flow

Source: https://www.pmi.org/pmbok-guide-standards/practice-guides/agile

Topics

#Just-in-Time (JIT)#Kanban#Agile Estimation#Flow-based Measurement