CAPM · Question #502
An organization uses a just-in-time (JIT) measurement system. What units should they use to estimate future work?
The correct answer is C. Cards. In a just-in-time (JIT) measurement system, work is estimated using cards, consistent with Kanban-style flow management where each card represents a unit of work pulled on demand.
Question
Options
- AHours
- BPoints
- CCards
- DPackages
How the community answered
(34 responses)- A3% (1)
- B3% (1)
- C88% (30)
- D6% (2)
Why each option
In a just-in-time (JIT) measurement system, work is estimated using cards, consistent with Kanban-style flow management where each card represents a unit of work pulled on demand.
Hours represent time-based estimation, which is more aligned with predictive planning and does not reflect the flow-based, pull-oriented nature of JIT systems.
Story points measure relative complexity and are used in sprint-based agile estimation, not specifically tied to JIT or Kanban flow measurement.
JIT systems focus on pulling work only when capacity is available, and in agile/Kanban contexts this is represented by cards - each card is a discrete work item that flows through the system one at a time. Cards as a unit of measurement align with JIT principles by limiting work-in-progress and making throughput visible rather than estimating effort in hours or abstract points.
Packages are not a standard unit of measurement in JIT or agile project management frameworks.
Concept tested: JIT measurement using cards in Kanban flow
Source: https://www.pmi.org/pmbok-guide-standards/practice-guides/agile