CAPM · Question #79

CAPM Question #79: Real Exam Question with Answer & Explanation

The correct answer is B: Pull communication. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

Options

  • APush communication
  • BPull communication
  • CInteractive communication
  • DStakeholder communication

Topics

#Communication methods#Pull communication#Lessons learned database#Information management