The correct answer is B: Pull communication. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
Options
- APush communication
- BPull communication
- CInteractive communication
- DStakeholder communication
Topics
#Communication methods#Pull communication#Lessons learned database#Information management