CAPM · Question #79
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication metho
Sign in or unlock CAPM to reveal the answer and full explanation for question #79. The question stem and answer options stay visible for context.
Project Management Fundamentals and Core Concepts
Question
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
Options
- APush communication
- BPull communication
- CInteractive communication
- DStakeholder communication
Unlock CAPM to see the answer
You've previewed enough free CAPM questions. Unlock CAPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Communication methods#Pull communication#Lessons learned database#Information management