CAPM · Question #78

In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?

The correct answer is C. They should be continuously engaged. A foundational principle of agile is continuous stakeholder engagement. In adaptive/agile life cycles, customers and sponsors actively collaborate with the team throughout the project - participating in iteration reviews, backlog refinement, sprint planning, and ongoing…

Agile Frameworks/Methodologies

Question

In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?

Options

  • AInvolvement is needed only during project initiation
  • BMinimal involvement of stakeholders is sufficient
  • CThey should be continuously engaged
  • DThey should be involved only during phase or deliverable reviews

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    90% (19)

Explanation

A foundational principle of agile is continuous stakeholder engagement. In adaptive/agile life cycles, customers and sponsors actively collaborate with the team throughout the project - participating in iteration reviews, backlog refinement, sprint planning, and ongoing prioritization. This continuous feedback loop enables the team to adapt scope based on evolving needs and deliver maximum value. Option A (only during initiation) and Option D (only during phase/deliverable reviews) both describe limited engagement, which is characteristic of predictive/waterfall projects. Option B (minimal involvement) contradicts agile principles, where the customer (often embodied as a product owner) is deeply engaged at all times.

Topics

#Agile Stakeholder Engagement#Adaptive Scope Management#Customer Involvement#Continuous Engagement

Community Discussion

No community discussion yet for this question.