CAPM · Question #78
CAPM Question #78: Real Exam Question with Answer & Explanation
The correct answer is C: They should be continuously engaged. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
Options
- AInvolvement is needed only during project initiation
- BMinimal involvement of stakeholders is sufficient
- CThey should be continuously engaged
- DThey should be involved only during phase or deliverable reviews
Topics
#Agile Stakeholder Engagement#Adaptive Scope Management#Customer Involvement#Continuous Engagement