In an agile or adaptive environment, when should risk be monitored and prioritized?

The correct answer is C. During each iteration as the project progresses. In agile and adaptive environments, risk management is a continuous, iterative activity - not confined to specific phases. Risks are identified, assessed, and prioritized during each iteration (sprint or cycle) as new information emerges and circumstances evolve. This reflects…

Agile Frameworks/Methodologies

Question

In an agile or adaptive environment, when should risk be monitored and prioritized?

Options

  • AOnly during the Initiation and Closing phases
  • BDuring the Initiation and Planning phases
  • CDuring each iteration as the project progresses
  • DThroughout the Planning process group and retrospective meeting

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    90% (19)

Explanation

In agile and adaptive environments, risk management is a continuous, iterative activity - not confined to specific phases. Risks are identified, assessed, and prioritized during each iteration (sprint or cycle) as new information emerges and circumstances evolve. This reflects a core agile principle: inspect and adapt continuously. Restricting risk monitoring to only the Initiation/Closing phases or only Planning is a predictive (waterfall) mindset. While retrospectives address process improvement, the full risk monitoring activity occurs throughout every iteration, not just retrospectives.