nerdexam
PMI

CAPM · Question #434

What tool or technique is primarily used to plan risk responses?

The correct answer is D. Risk management plan. The Risk Management Plan is the foundational document that governs how risk response planning is conducted - it defines the methodology, roles, risk thresholds, and timing for all risk processes including Plan Risk Responses. It serves as both an input and a guiding framework…

Predictive, Plan-Based Methodologies

Question

What tool or technique is primarily used to plan risk responses?

Options

  • ARisk categorization
  • BProject risk document updates
  • CStrategies for overall project risk
  • DRisk management plan

How the community answered

(47 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    4% (2)
  • D
    91% (43)

Explanation

The Risk Management Plan is the foundational document that governs how risk response planning is conducted - it defines the methodology, roles, risk thresholds, and timing for all risk processes including Plan Risk Responses. It serves as both an input and a guiding framework that shapes which strategies are appropriate to apply. Risk categorization (A) is used in risk identification and analysis processes. Project risk document updates (B) are outputs, not tools. Strategies for overall project risk (C) are a technique within Plan Risk Responses, but the risk management plan is the overarching tool that directs the entire risk response planning effort.

Topics

#Risk Management#Plan Risk Responses#Risk Management Plan#Project Planning

Community Discussion

No community discussion yet for this question.

Full CAPM Practice