CAPM · Question #225
Which tasks should a project manager accomplish in order to manage project scope correctly?
The correct answer is C. Plan Scope Management; Collect Requirements; Define, Validate, and Control Scope; and Create WBS. The PMBOK Guide defines six processes within the Scope Management Knowledge Area: Plan Scope Management, Collect Requirements, Define Scope, Create WBS, Validate Scope, and Control Scope. Option C correctly lists all of these processes. Option A is incorrect because it includes…
Question
Options
- ADefine, Validate, and Control Scope; Control Schedule; Control Costs and Manage Stakeholder Engagement.
- BCollect Requirements, Define Scope, Create WBS, Develop Schedule, and Manage Stakeholder Engagement.
- CPlan Scope Management; Collect Requirements; Define, Validate, and Control Scope; and Create WBS.
- DDefine, Validate, and Control Scope; Control Costs; Manage Stakeholder Engagement; and keep budget under control.
How the community answered
(34 responses)- A6% (2)
- C91% (31)
- D3% (1)
Explanation
The PMBOK Guide defines six processes within the Scope Management Knowledge Area: Plan Scope Management, Collect Requirements, Define Scope, Create WBS, Validate Scope, and Control Scope. Option C correctly lists all of these processes. Option A is incorrect because it includes 'Control Schedule' and 'Control Costs,' which belong to the Schedule and Cost Management knowledge areas, not Scope. Option B is incorrect because 'Develop Schedule' is a Schedule Management process, not a Scope process. Option D is also incorrect for including 'Control Costs' as part of scope management.