CAPM · Question #225

Which tasks should a project manager accomplish in order to manage project scope correctly?

The correct answer is C. Plan Scope Management; Collect Requirements; Define, Validate, and Control Scope; and Create WBS. The PMBOK Guide defines six processes within the Scope Management Knowledge Area: Plan Scope Management, Collect Requirements, Define Scope, Create WBS, Validate Scope, and Control Scope. Option C correctly lists all of these processes. Option A is incorrect because it includes…

Predictive, Plan-Based Methodologies

Question

Which tasks should a project manager accomplish in order to manage project scope correctly?

Options

  • ADefine, Validate, and Control Scope; Control Schedule; Control Costs and Manage Stakeholder Engagement.
  • BCollect Requirements, Define Scope, Create WBS, Develop Schedule, and Manage Stakeholder Engagement.
  • CPlan Scope Management; Collect Requirements; Define, Validate, and Control Scope; and Create WBS.
  • DDefine, Validate, and Control Scope; Control Costs; Manage Stakeholder Engagement; and keep budget under control.

How the community answered

(34 responses)
  • A
    6% (2)
  • C
    91% (31)
  • D
    3% (1)

Explanation

The PMBOK Guide defines six processes within the Scope Management Knowledge Area: Plan Scope Management, Collect Requirements, Define Scope, Create WBS, Validate Scope, and Control Scope. Option C correctly lists all of these processes. Option A is incorrect because it includes 'Control Schedule' and 'Control Costs,' which belong to the Schedule and Cost Management knowledge areas, not Scope. Option B is incorrect because 'Develop Schedule' is a Schedule Management process, not a Scope process. Option D is also incorrect for including 'Control Costs' as part of scope management.

Topics

#Project Scope Management#PMBOK Processes#Scope Management Processes#Work Breakdown Structure (WBS)