The correct answer is B: Ensures that all the information needs of the project and the stakeholders are met. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which statement describes the Monitor Communications process?
Options
- AEvaluates the differences between the communications management plan and the reality of communications in a project
- BEnsures that all the information needs of the project and the stakeholders are met
- CEnsures that project information is created, collected, and distributed in a timely and appropriate manner
- DDevelops an appropriate and plan for communication of project activities