CAPM · Question #55
A project it just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
The correct answer is B. Stakeholder satisfaction should be identified immediately and managed as a project objective.. The PMBOK Guide emphasizes that stakeholder identification should begin as early as possible - ideally during project initiation - and that stakeholder satisfaction is a legitimate project objective to be actively managed throughout the project. Option A is incorrect because stak
Question
Options
- AThe project manager should identify and deal with stakeholders only during the execution phase.
- BStakeholder satisfaction should be identified immediately and managed as a project objective.
- CThe project manager should focus on project objectives and deal with stakeholders as a secondary priority.
- DStakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
How the community answered
(58 responses)- A2% (1)
- B95% (55)
- C3% (2)
Explanation
The PMBOK Guide emphasizes that stakeholder identification should begin as early as possible - ideally during project initiation - and that stakeholder satisfaction is a legitimate project objective to be actively managed throughout the project. Option A is incorrect because stakeholder engagement is not limited to execution. Option C is incorrect because stakeholders are a primary concern, not secondary. Option D goes too far by making stakeholder satisfaction the most important goal above project objectives - the correct view is that they are both managed together, not one subordinating the other.