The correct answer is A: Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of the following set of elements is part of an effective communications management plan?
Options
- AEscalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information
- BPhone book directory, stakeholder communication requirements, project charter, glossary of common terminology
- COrganizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology
- DGlossary of common terminology, constraints derived from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan
Topics
#Communications Management Plan#Project Communications#Project Planning#Plan Components