CAPM · Question #56

CAPM Question #56: Real Exam Question with Answer & Explanation

The correct answer is A: Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which of the following set of elements is part of an effective communications management plan?

Options

  • AEscalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information
  • BPhone book directory, stakeholder communication requirements, project charter, glossary of common terminology
  • COrganizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology
  • DGlossary of common terminology, constraints derived from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan

Topics

#Communications Management Plan#Project Communications#Project Planning#Plan Components