nerdexam
PMIPMI

CAPM · Question #66

CAPM Question #66: Real Exam Question with Answer & Explanation

The correct answer is C: Additional duration estimates in response to identified risks that have been accepted. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

How can a project manager represent a contingency reserve in the schedule?

Options

  • AAdditional weeks of work to account for unknown-unknowns risks
  • BTask duration estimates of the best case scenarios
  • CAdditional duration estimates in response to identified risks that have been accepted
  • DMilestones representing the completion of deliverables

Topics

#Contingency Reserve#Schedule Management#Risk Management#Project Planning

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions