PMIPMI
CAPM · Question #66
CAPM Question #66: Real Exam Question with Answer & Explanation
The correct answer is C: Additional duration estimates in response to identified risks that have been accepted. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
How can a project manager represent a contingency reserve in the schedule?
Options
- AAdditional weeks of work to account for unknown-unknowns risks
- BTask duration estimates of the best case scenarios
- CAdditional duration estimates in response to identified risks that have been accepted
- DMilestones representing the completion of deliverables
Topics
#Contingency Reserve#Schedule Management#Risk Management#Project Planning
Community Discussion
No community discussion yet for this question.