nerdexam
PMIPMI

CAPM · Question #65

CAPM Question #65: Real Exam Question with Answer & Explanation

The correct answer is A: Budgeted work that has been completed. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

What does earned value (EV) measure?

Options

  • ABudgeted work that has been completed
  • BTotal costs incurred while accomplishing work
  • CBudget associated with planned work
  • DCost efficiency of budgeted resources

Topics

#Earned Value (EV)#Earned Value Management (EVM)#Project Performance Measurement#Cost Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions