nerdexam
PMIPMI

CAPM · Question #64

CAPM Question #64: Real Exam Question with Answer & Explanation

The correct answer is C: All team members throughout the project life cycle. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

In a project using agile methodology, who may perform the quality control activities?

Options

  • AA group of quality experts at specific times during the project
  • BThe project manager only
  • CAll team members throughout the project life cycle
  • DSelected stakeholders at specific times during the project

Topics

#Agile Quality Control#Team Responsibilities#Agile Principles

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions