nerdexam
PMI

CAPM · Question #63

In which Project Cost Management process is work performance data included?

The correct answer is D. Control Costs. Work performance data is an input exclusively to the Control Costs process, where actual cost data is compared against the cost baseline to assess project performance.

Predictive, Plan-Based Methodologies

Question

In which Project Cost Management process is work performance data included?

Options

  • APlan Cost Management
  • BEstimate Costs
  • CDetermine Budget
  • DControl Costs

How the community answered

(15 responses)
  • A
    7% (1)
  • C
    7% (1)
  • D
    87% (13)

Why each option

Work performance data is an input exclusively to the Control Costs process, where actual cost data is compared against the cost baseline to assess project performance.

APlan Cost Management

Plan Cost Management is a planning process that establishes policies and procedures for managing costs; it does not use work performance data as an input.

BEstimate Costs

Estimate Costs is a planning process focused on approximating costs of resources; it does not receive work performance data.

CDetermine Budget

Determine Budget aggregates cost estimates to establish the cost baseline; it is also a planning process and does not use work performance data.

DControl CostsCorrect

Control Costs is a monitoring and controlling process that receives work performance data - such as actual costs incurred - as a key input to calculate variances and forecasts. It uses this raw data to produce work performance information, including cost variance (CV) and schedule variance (SV). The other cost management processes occur before execution and therefore do not consume work performance data.

Concept tested: Control Costs process inputs in PMBOK

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project Cost Management#Control Costs#Work Performance Data#PMBOK Processes

Community Discussion

No community discussion yet for this question.

Full CAPM Practice