nerdexam
PMIPMI

CAPM · Question #62

CAPM Question #62: Real Exam Question with Answer & Explanation

The correct answer is C: Communications management plan and stakeholder engagement plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

The project manager implemented the stakeholder engagement plan and realized that some updates should be made. Which components of the project management plan should be modified?

Options

  • AProject charter and stakeholder engagement plan
  • BRisk management plan and stakeholder engagement plan
  • CCommunications management plan and stakeholder engagement plan
  • DProject charter and communications management plan

Topics

#Stakeholder Engagement#Communications Management#Project Plan Updates

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions