PMIPMI
CAPM · Question #62
CAPM Question #62: Real Exam Question with Answer & Explanation
The correct answer is C: Communications management plan and stakeholder engagement plan. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
The project manager implemented the stakeholder engagement plan and realized that some updates should be made. Which components of the project management plan should be modified?
Options
- AProject charter and stakeholder engagement plan
- BRisk management plan and stakeholder engagement plan
- CCommunications management plan and stakeholder engagement plan
- DProject charter and communications management plan
Topics
#Stakeholder Engagement#Communications Management#Project Plan Updates
Community Discussion
No community discussion yet for this question.