nerdexam
PMIPMI

CAPM · Question #94

CAPM Question #94: Real Exam Question with Answer & Explanation

The correct answer is A: Scope and impact of change to stakeholders. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Due to new market conditions a five-year project requires a full revision of project objectives. Which components of the stakeholder engagement plan need to be updated?

Options

  • AScope and impact of change to stakeholders
  • BProject scope and stakeholder goals
  • CEngagement level of key stakeholders
  • DStakeholder expectations for the project

Topics

#Stakeholder Management#Change Management#Project Objectives#Project Scope

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions