PMIPMI
CAPM · Question #94
CAPM Question #94: Real Exam Question with Answer & Explanation
The correct answer is A: Scope and impact of change to stakeholders. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Due to new market conditions a five-year project requires a full revision of project objectives. Which components of the stakeholder engagement plan need to be updated?
Options
- AScope and impact of change to stakeholders
- BProject scope and stakeholder goals
- CEngagement level of key stakeholders
- DStakeholder expectations for the project
Topics
#Stakeholder Management#Change Management#Project Objectives#Project Scope
Community Discussion
No community discussion yet for this question.