PMIPMI
CAPM · Question #93
CAPM Question #93: Real Exam Question with Answer & Explanation
The correct answer is C: Decomposition. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?
Options
- ARolling wave planning
- BExpert judgment
- CDecomposition
- DData analysis
Topics
#Decomposition#Effort Estimation#Scope Definition#Work Breakdown Structure
Community Discussion
No community discussion yet for this question.