nerdexam
PMIPMI

CAPM · Question #93

CAPM Question #93: Real Exam Question with Answer & Explanation

The correct answer is C: Decomposition. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?

Options

  • ARolling wave planning
  • BExpert judgment
  • CDecomposition
  • DData analysis

Topics

#Decomposition#Effort Estimation#Scope Definition#Work Breakdown Structure

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions