nerdexam
PMI

CAPM · Question #86

In which of the Risk Management processes is the project charter used as an input?

The correct answer is C. Plan Risk Management. The project charter is used as an input to the Plan Risk Management process because it contains the high-level project information needed to frame the risk management approach.

Predictive, Plan-Based Methodologies

Question

In which of the Risk Management processes is the project charter used as an input?

Options

  • APlan Risk Responses
  • BImplement Risk Responses
  • CPlan Risk Management
  • DPerform Quantitative Risk Responses

How the community answered

(53 responses)
  • A
    2% (1)
  • C
    94% (50)
  • D
    4% (2)

Why each option

The project charter is used as an input to the Plan Risk Management process because it contains the high-level project information needed to frame the risk management approach.

APlan Risk Responses

Plan Risk Responses uses the risk register and risk report as primary inputs - the project charter is not an input to this process because responses are developed after risks are identified and analyzed.

BImplement Risk Responses

Implement Risk Responses uses the risk register, project plan, and lessons learned register as inputs - the project charter is not referenced at this execution-level process.

CPlan Risk ManagementCorrect

Plan Risk Management defines how risk management activities will be conducted throughout the project, and it requires the project charter as an input because the charter provides foundational information such as project objectives, high-level risks, summary milestones, and pre-approved financial resources. This information establishes the context for determining risk thresholds, methodology, roles, and the level of risk management rigor appropriate for the project. Without this context, a meaningful risk management plan cannot be developed.

DPerform Quantitative Risk Responses

Perform Quantitative Risk Analysis is not a standard PMBOK process name; Perform Quantitative Risk Analysis uses the risk register, risk report, and project schedule as inputs - not the project charter.

Concept tested: Plan Risk Management inputs - project charter

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management#Project Charter#PMI Processes#Process Inputs

Community Discussion

No community discussion yet for this question.

Full CAPM Practice