nerdexam
PMIPMI

CAPM · Question #86

CAPM Question #86: Real Exam Question with Answer & Explanation

The correct answer is C: Plan Risk Management. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

In which of the Risk Management processes is the project charter used as an input?

Options

  • APlan Risk Responses
  • BImplement Risk Responses
  • CPlan Risk Management
  • DPerform Quantitative Risk Responses

Topics

#Risk Management#Project Charter#PMI Processes#Process Inputs

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions