PMIPMI
CAPM · Question #86
CAPM Question #86: Real Exam Question with Answer & Explanation
The correct answer is C: Plan Risk Management. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
In which of the Risk Management processes is the project charter used as an input?
Options
- APlan Risk Responses
- BImplement Risk Responses
- CPlan Risk Management
- DPerform Quantitative Risk Responses
Topics
#Risk Management#Project Charter#PMI Processes#Process Inputs
Community Discussion
No community discussion yet for this question.