nerdexam
PMI

CAPM · Question #85

What is the best tool to calculate the critical path on a project?

The correct answer is D. Project network diagram. A project network diagram is the best tool for calculating the critical path because it visually maps all activity sequences and dependencies needed to apply the Critical Path Method.

Predictive, Plan-Based Methodologies

Question

What is the best tool to calculate the critical path on a project?

Options

  • ACritical chain method
  • BGraphical evaluation and review technique (GERT) diagram
  • CGantt chart
  • DProject network diagram

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    7% (2)
  • D
    87% (26)

Why each option

A project network diagram is the best tool for calculating the critical path because it visually maps all activity sequences and dependencies needed to apply the Critical Path Method.

ACritical chain method

The critical chain method is a scheduling technique that accounts for resource constraints and uses buffers to protect the project completion date - it is an alternative scheduling approach, not a tool for calculating the critical path.

BGraphical evaluation and review technique (GERT) diagram

A GERT diagram supports probabilistic and conditional branching in schedules but is rarely used in practice and is not the standard tool for critical path calculation.

CGantt chart

A Gantt chart displays activities on a timeline bar chart and can show the critical path after it is calculated, but it does not provide the dependency network structure needed to calculate it.

DProject network diagramCorrect

The project network diagram depicts all project activities as nodes or arrows connected by dependency relationships, providing the complete logical sequence required to perform Critical Path Method (CPM) analysis. By tracing all paths through the network and calculating Early Start, Early Finish, Late Start, and Late Finish dates, the project manager can identify the longest path - the critical path - and determine float for each activity. No other tool provides this complete dependency mapping required for CPM.

Concept tested: Critical Path Method and project network diagrams

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Critical Path Method (CPM)#Project Network Diagram#Schedule Management#Project Planning

Community Discussion

No community discussion yet for this question.

Full CAPM Practice