The correct answer is D: When the project charter is produced, at the beginning of each phase, and when significant changes occur. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
At what stages of a project should the Identify Stakeholders process be performed?
Options
- AWhen beginning each phase of the project
- BAt the beginning of the project only
- COnly when the project manager is concerned about stakeholder satisfaction
- DWhen the project charter is produced, at the beginning of each phase, and when significant changes occur
Topics
#Identify Stakeholders#Stakeholder Management#Project Lifecycle#Process Timing