CAPM Question #68: Real Exam Question with Answer & Explanation

The correct answer is A: Manage Quality is all about following planned processes and procedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which statement describes the relationship between Manage Quality process and Control Quality process?

Options

  • AManage Quality is all about following planned processes and procedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.
  • BControl Quality is all about following planned process and procedures for quality, while Manage Quality is about making making sure that the product which is produced conforms to customer specifications.
  • CManage Quality and Control Quality are the same.
  • DManage Quality is part of Quality Management and Control Quality is a subset of the Stakeholder Management Process group.