CAPM · Question #53
Which set of activities should a project manager use as part of the Develop Team process?
The correct answer is C. Conflict management activities and tracking team performance. The Develop Team process focuses on improving team member competencies and the overall team environment to enhance project performance. Tracking team performance is a core part of assessing whether development efforts are effective, and conflict management helps maintain a produc
Question
Options
- ATraining and establishing ground rules
- BNetworking activities and establishing team resources
- CConflict management activities and tracking team performance
- DRecruit new team members and training
How the community answered
(33 responses)- A3% (1)
- B6% (2)
- C88% (29)
- D3% (1)
Explanation
The Develop Team process focuses on improving team member competencies and the overall team environment to enhance project performance. Tracking team performance is a core part of assessing whether development efforts are effective, and conflict management helps maintain a productive team environment. Option A (training and ground rules) is partially correct but is more commonly associated with planning team norms. Option B (networking and establishing resources) relates more to resource planning and acquisition. Option D (recruiting) belongs to the Acquire Resources process, not Develop Team.