CAPM · Question #52

Which is a list of organizational systems that may have an impact on a project?

The correct answer is C. Organizational structure, governance framework, and management elements. According to the PMBOK Guide, an organizational system is defined by three key components: organizational structure (how the organization is arranged, e.g., functional, matrix, projectized), governance framework (the policies and rules under which the organization operates), and

Project Management Fundamentals and Core Concepts

Question

Which is a list of organizational systems that may have an impact on a project?

Options

  • AInternal policies, company procedures, and organizational resources
  • BCompany culture, purchasing system, and project management information system
  • COrganizational structure, governance framework, and management elements
  • DOrganizational process assets, enterprise environmental factors, and corporate knowledge

How the community answered

(18 responses)
  • A
    6% (1)
  • C
    89% (16)
  • D
    6% (1)

Explanation

According to the PMBOK Guide, an organizational system is defined by three key components: organizational structure (how the organization is arranged, e.g., functional, matrix, projectized), governance framework (the policies and rules under which the organization operates), and management elements (the people, processes, and tools used to manage the organization). Option A describes resources and policies. Option B blends enterprise environmental factors (EEFs). Option D refers to broader PMBOK input categories (OPAs and EEFs), not the definition of an organizational system itself.

Topics

#Organizational Systems#Project Environment#Organizational Influences#Governance