CAPM · Question #52

CAPM Question #52: Real Exam Question with Answer & Explanation

The correct answer is C: Organizational structure, governance framework, and management elements. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

Which is a list of organizational systems that may have an impact on a project?

Options

  • AInternal policies, company procedures, and organizational resources
  • BCompany culture, purchasing system, and project management information system
  • COrganizational structure, governance framework, and management elements
  • DOrganizational process assets, enterprise environmental factors, and corporate knowledge

Topics

#Organizational Systems#Project Environment#Organizational Influences#Governance