nerdexam
PMIPMI

CAPM · Question #51

CAPM Question #51: Real Exam Question with Answer & Explanation

The correct answer is A: Time and material (T&M). See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager needs to request outside support for a statement of work (SOW) that is not precise. Which kind of contract does the project manager need to create?

Options

  • ATime and material (T&M)
  • BCost plus fixed fee (CPFF)
  • CFixed price
  • DCost plus award fee (CPAF)

Topics

#Contract types#Procurement management#Statement of Work (SOW)#Time and material (T&M)

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions