CAPM · Question #51
A project manager needs to request outside support for a statement of work (SOW) that is not precise. Which kind of contract does the project manager need to create?
The correct answer is A. Time and material (T&M). A Time and Material (T&M) contract is best suited when the scope of work is not well-defined or precise. It allows payment based on actual hours worked and materials consumed, providing the flexibility needed when requirements are unclear. Fixed-price contracts require a precise,
Question
Options
- ATime and material (T&M)
- BCost plus fixed fee (CPFF)
- CFixed price
- DCost plus award fee (CPAF)
How the community answered
(19 responses)- A95% (18)
- B5% (1)
Explanation
A Time and Material (T&M) contract is best suited when the scope of work is not well-defined or precise. It allows payment based on actual hours worked and materials consumed, providing the flexibility needed when requirements are unclear. Fixed-price contracts require a precise, well-defined scope to set a firm price. Cost-plus contracts (CPFF and CPAF) are typically used for research or development where costs are genuinely uncertain, not simply because the SOW is vague. T&M strikes the right balance by accommodating an imprecise SOW while still allowing work to begin.
Topics
Community Discussion
No community discussion yet for this question.