CAPM · Question #99
The Agile principle "welcome changing requirements, even late in development" relates to which agile manifesto?
The correct answer is D. Responding to change over following a plan. The Agile principle of welcoming late-changing requirements directly embodies the fourth Agile Manifesto value of responding to change over following a plan.
Question
Options
- AWorking software over comprehensive documentation
- BIndividuals and interactions over processes and tools
- CCustomer collaboration over contract negotiation
- DResponding to change over following a plan
How the community answered
(28 responses)- A4% (1)
- C4% (1)
- D93% (26)
Why each option
The Agile principle of welcoming late-changing requirements directly embodies the fourth Agile Manifesto value of responding to change over following a plan.
The value of working software over comprehensive documentation addresses the form of deliverables and how progress is measured, not the team's posture toward changing requirements.
Individuals and interactions over processes and tools addresses team collaboration and human communication preferences, not adaptability to requirement changes.
Customer collaboration over contract negotiation emphasizes the nature of the customer relationship and partnership, not specifically the acceptance of late-stage requirement changes.
The fourth Agile Manifesto value explicitly states preference for 'responding to change over following a plan.' The principle of welcoming changing requirements, even late in development, is a direct practical expression of this value, emphasizing that the ability to adapt delivers greater customer value than rigid adherence to a predetermined plan.
Concept tested: Agile Manifesto values and corresponding principles
Source: https://agilemanifesto.org/principles.html
Topics