CAPM · Question #90

CAPM Question #90: Real Exam Question with Answer & Explanation

The correct answer is A: Interactive. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

Options

  • AInteractive
  • BPush
  • CVerbal
  • DOral

Topics

#Project Communication#Communication Methods#Delegation