PMIPMI
CAPM · Question #60
CAPM Question #60: Real Exam Question with Answer & Explanation
The correct answer is B: Project management plan, project documents, enterprise environmental factors, and organizational process assets. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What are the inputs of the Estimate Costs process?
Options
- AProject management plan, work performance data, enterprise environmental factors, and organizational process assets
- BProject management plan, project documents, enterprise environmental factors, and organizational process assets
- CCost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
- DProject management plan, enterprise environmental factors, basis of estimates, and organizational process assets
Topics
#Estimate Costs#Cost Management#Inputs#Project Management Process
Community Discussion
No community discussion yet for this question.