nerdexam
PMIPMI

CAPM · Question #60

CAPM Question #60: Real Exam Question with Answer & Explanation

The correct answer is B: Project management plan, project documents, enterprise environmental factors, and organizational process assets. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What are the inputs of the Estimate Costs process?

Options

  • AProject management plan, work performance data, enterprise environmental factors, and organizational process assets
  • BProject management plan, project documents, enterprise environmental factors, and organizational process assets
  • CCost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
  • DProject management plan, enterprise environmental factors, basis of estimates, and organizational process assets

Topics

#Estimate Costs#Cost Management#Inputs#Project Management Process

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions