CAPM · Question #59
What process is included in Project Integration Management?
The correct answer is A. Monitor and Control Project Work. Project Integration Management contains seven processes per the PMBOK Guide: Develop Project Charter, Develop Project Management Plan, Direct and Manage Project Work, Manage Project Knowledge, Monitor and Control Project Work, Perform Integrated Change Control, and Close Project
Question
Options
- AMonitor and Control Project Work
- BControl Scope
- CControl Schedule
- DDevelop Team
How the community answered
(50 responses)- A88% (44)
- B6% (3)
- C2% (1)
- D4% (2)
Explanation
Project Integration Management contains seven processes per the PMBOK Guide: Develop Project Charter, Develop Project Management Plan, Direct and Manage Project Work, Manage Project Knowledge, Monitor and Control Project Work, Perform Integrated Change Control, and Close Project or Phase. 'Monitor and Control Project Work' (Option A) is one of these. 'Control Scope' (Option B) belongs to Project Scope Management. 'Control Schedule' (Option C) belongs to Project Schedule Management. 'Develop Team' (Option D) belongs to Project Resource Management.
Topics
Community Discussion
No community discussion yet for this question.