nerdexam
PMIPMI

CAPM · Question #74

CAPM Question #74: Real Exam Question with Answer & Explanation

The correct answer is A: Appraisal costs. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

After an internal deliverable review session with the team, the project manager identifies some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and time for the required rework. How would the project manager define these extra costs?

Options

  • AAppraisal costs
  • BManagement reserves
  • CCost of nonconformance
  • DCost of conformance

Topics

#Quality Management#Cost of Quality#Appraisal Costs#Rework

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions