PMIPMI
CAPM · Question #74
CAPM Question #74: Real Exam Question with Answer & Explanation
The correct answer is A: Appraisal costs. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
After an internal deliverable review session with the team, the project manager identifies some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and time for the required rework. How would the project manager define these extra costs?
Options
- AAppraisal costs
- BManagement reserves
- CCost of nonconformance
- DCost of conformance
Topics
#Quality Management#Cost of Quality#Appraisal Costs#Rework
Community Discussion
No community discussion yet for this question.